What is the practice for overcoming the 999 events limit of the CMX3600 format? Can we load several EDLs at the same time? How should I organize a VK project?

When using the CMX3600 format, the limit for an EDL is 999 changes per iteration. So if a project exceeds this limit you have to split it into multiple edls. You can load the multiple EDLs into VK and it will run it sequentially.

The organization of the project depends on your convenience (basically the number of iterations you want to work with). You can use 2, 3 or 4 edls in the project or divide it according to chapter/scenes. But the main thing is to organize the project around the limit of 999 events per edl.